Timeline of Events

Below is a timeline of each step of our land and build progress.

05/05/2017 - POOL - Solar heating installed on roof

01/05/2017 - POOL - Pool coping concrete installed to hold pool in place

28/04/2017 - BUILD - Appliances, heating/cooling installed. Pool equipment installed

27/04/2017 - POOL - Pool lowered into hole

26/04/2017 - POOL - Pool hole finished excavation and pool delivered

24/04/2017 - OTHER - Quote for office cabinetry and glass pet door installed.

24/04/2017 - OTHER - LHS Fence completed

24/04/2017 - POOL - Pool construction starts

22/04/2017 - OTHER - LHS Fence started

20/04/2017 - OTHER - Driveway construction finishes

18/04/2017 - OTHER - Driveway construction starts

12/04/2017 - OTHER - Blinds Installed

07/04/2017 - BUILD - Received Keys and Handover Completed

31/03/2017 - BANK - Final Progress Payment Paid

31/03/2017 - BUILD - Follow up on QA Inspection

27/03/2017 - BUILD - QA Inspection with Independent Inspector

17/03/2017 - BUILD - Most fixtures and fittings installed.

17/03/2017 - BUILD - Carpet Laid

10/03/2017 - POOL - Receive building permit for pool

10/03/2017 - BUILD - Electrical Works Start - Tiling completed

06/03/2017 - BUILD - All tiles laid and ready for mortar

02/03/2017 - BUILD - Floor leveling completed. Tiling starts. Glass splash-back installed in kitchen

22/02/2017 - BUILD - Caesarstone benches installed. Floor leveling for the tiling starts.

15/02/2017 - POOL - Rainwise lodge building permit in preparation for construction in March/April.

13/02/2017 - BUILD - First coats of painting have occured. Front Facade has been rendered

13/02/2017 - OTHER - Meeting on site with Fence company to arrange fence quote.

09/02/2017 - OTHER - Meeting on site with Concreting company to arrange driveway quote.

08/02/2017 - BUILD - Plastic put up in windows in preparation of painting starting.

02/02/2017 - OTHER - Meeting on site with Blind company to measure and choose colours

02/02/2017 - BUILD - PrePlaster/Waterproofing inspection takes place

17/01/2017 - BUILD - Cement sheeting installed in eaves.

16/01/2017 - BUILD - Kitchen and Bathroom cabinetry installed

16/01/2017 - BUILD - Skirting installed around windows and all internal doors hung.

13/01/2017 - BUILD - Plaster and cornice inside completed

06/01/2017 - BANK - Progress payment for external lock up received and paid.

24/12/2016 - BUILD - External lock up stage achieved (brick work complete)

15/12/2016 - BANK - Progress payment for frame stage received and paid.

15/12/2016 - BUILD- Plaster commences inside and Bricks start getting laid.

12/12/2016 - BUILD- Insulation installed

09/12/2016 - BUILD - Most plumbing and electrical completed. Insulation installed

09/12/2016 - BUILD - Independent inspection completed on Pre-plaster stage

07/12/2016 - BUILD - Bricks delivered to site.

02/12/2016 - BUILD - Roof installed and plumbing and electrical starts

27/11/2016 - BUILD - Gutters installed and roof tiles delivered to site

21/11/2016 - BUILD - Independent inspection completed on Slab/Frame stages

18/11/2016 - BUILD - Frame reaches completion

15/11/2016 - BUILD - Frame construction starts

07/11/2016 - BANK - Progress payment for slab stage received and paid

05/11/2016 - BUILD - Slab pour completed

03/11/2016 - BUILD - Slab foundation laid

29/09/2016 - BUILD - First signs of digging and site works

13/09/2016 - BUILD - Fence placed around block in preparation of works.

07/09/2016 - BUILD - Build file passed to construction phase

02/09/2016 - BUILD - Final quality assurance checks of build completed

29/08/2016 - BUILD - Received building permit from Council

23/08/2016 - BANK - Received formal loan approval for Land and Build

11/08/2016 - BUILD - Received developer approval for build

20/07/2016 - BANK - Meeting with mortgage broker to sign formal loan paperwork

19/07/2016 - BANK - Received formal finance for Land/Construction/Pool Loan

13/07/2016 - BANK - Valuation of Land and build takes place

23/06/2016 - LAND - Land settles and land loan matures

16/06/2016 - LAND - Land construction finishes and Titles

10/06/2016 - BANK - Signed formal loan documents for Land with broker

08/06/2016 - BANK - Received formal loan approval for land

12/05/2016 - POOL - Sign contracts for Pool and paid deposit

05/04/2016 - POOL - Meeting with Rainwise Pools to discuss pool quote

16/03/2016 - BUILD - Electrical Appointment at Boutique Head Office

10/03/2016 - BUILD - Colour Appointment and Contract Signing at Boutique Head Office

03/02/2016 - BUILD - Walked through Hynes Tiles to see Full Range

15/01/2016 - BANK - Received conditional approval for Land + Construction Loan

13/01/2016 - BUILD - Signing of PWC (Preliminary Works Contract) at Boutiqe Head Office

08/01/2016 - BUILD - Completed second walk through of St Tropez

03/01/2016 - BUILD - Completed first walk through of St Tropez 28 Display Home

23/11/2015 - LAND - Balance of 10% of land purchase paid to developer

18/11/2015 - LAND - Signed land contracts and paid further $10,000 deposit to confirm purchase

16/11/2015 - LAND - Received contracts and sent to conveyancer to read over

15/11/2015 - BANK - Contacted mortage broker and arranged conditional approval for land loan

15/11/2015 - LAND - Placed $1000 deposit to secure place in development release